ALBA Potline 6, Manama, 巴林

  • 建筑类型:
  • 能源设施
全屏地图 关闭

Peikko has delivered a substantial order of connection items to an expansion of an aluminium smelter plant located in Bahrain. The order comprises more than 10 000 pieces of HPKM® Column Shoes and HPM® Rebar Anchor Bolts for the plant’s column connections. The current Line 6 Expansion Project will make Aluminium Bahrain the largest single site aluminium smelter in the world.

“This project is one of the biggest industrial projects in Bahrain with a strong interest from the Bahraini government. We are honored that Peikko was chosen as a supplier for this significant plant investment. Decisive for this project was the fast and safe on-site assembly of Peikko’s column connections, which accelerates the frame erection phase. Also our effective software tools for the design of column connections were appreciated”, states Topi Paananen, CEO of Peikko Group Corporation.

阅读更多 down-arrow.png

项目概览

开发商:
Aluminium Bahrain ALBA
施工单位:
Nass Contracting
结构设计师:
Bechtel Corporation
构件生产商:
Nass Contracting / Delmon Precast
交付年份:
2017
完成时间:
2019

我们提供的解决方案

联系我们

Cesar Molina

Cesar Molina

Project Manager

Saudi Arabia

[email protected]